Current work involves preparation for curbing installation. There has been a delay on scheduling a subcontractor for curbing installation, but work should begin the week of October 27. Work on other lead time items, such as pavers and flashers, will follow. Work should be completed by the end of November.
Click here to view an approximate schedule for the work.
If you have any questions, please telephone the Engineering Division at 978-671-1300 or contact us.