Posted on: October 24, 2014

[ARCHIVED] Paving Program

Work on River Street is essentially complete, with only punch list items remaining. Improvements were made at the intersection with Nashua Road & Rangeway Road involving sight lines and new signage.

Work is essentially complete with only punch list items remaining on the following roads: Woodlawn Avenue, Basswood Avenue, New Foster Avenue, Applewood Avenue, Dartmouth Dr, Magnolia Avenue, and Hancock Street.

The Contractor is working on the following roads: Baniulis Rd, Charles Anna Ln, David Rd, Nolte Rd, Phyllis Dr, Treble Terrace. Remaining work includes driveway aprons, loam & seed, line striping, and other minor items.

Work on the following roads continues: Jenkins Dr, Meadow Glen Rd, Old Treble Cove Rd. Top coat paving is scheduled for October 25.

Work on the following roads continues: Cook St, guardrail installation should occur the week of October 27. Top coat paving may be scheduled before November 15. Webb Brook Rd, top coat paving and intersection work at Allen Road will not occur until next spring. The remaining section of Webb Brook Road from the Elks to Boston Road is part of another contract and should be paved before November 15.

Crosswalk work on Middlesex Turnpike at Micozzi Beach: paving is scheduled for October 25. Remaining work includes fencing modifications, and the installation of pedestrian flasher equipment.

Due to timing limitations, Springs Road work will need to be delayed until next spring.

If you have any questions, please telephone the Engineering Division at 978-671-1300 or contact us.