[ARCHIVED] Middlesex Turnpike Phase 3 - Updated 6/30/2022

Please be advised that work is ongoing on the Middlesex Turnpike Phase 3 Project:

On July 7, 2022, the Contractor is scheduled to begin reclaiming and grading the roadway between Manning Road and the Mobile Station.  Traffic in both directions will be allowed to pass through the project area during this work. Travel lanes will be shifted and traffic officers will be present to assist guiding vehicles through the work area.

Following reclamation of the roadway, grading will continue.  Paving in this area is tentatively scheduled to begin on July 19, 2022.

----------------------

Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below.  We have included the Contractor's 4-week look ahead schedule, an overall schedule by stages, and a copy of the project plans.  The 4-week look ahead schedule will be updated regularly.

This work is part of a $35 million transportation improvement project in Bedford and Billerica and is currently scheduled to be completed in 2023.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.