The Contractor has provided the following tentative schedule:
Intersection of Middlesex Turnpike and Manning Road: Preparation for drainage work at the will begin Thursday, 5/18/23. Drainage work is tentatively scheduled at this intersection on Saturday and Sunday 5/20-5/21 pending Town approval. Pavement reclaim and grading will occur the week of 5/31. Paving of this intersection is currently scheduled for Friday, 6/9.
Intersection of Middlesex Turnpike and Lexington Road: Milling is scheduled for Saturday 5/20, followed by grading Monday, 5/22 through Wednesday, 5/24. Paving is scheduled for Thursday 5/25.
----------------------
Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below. We have included the Contractor's 4-week look ahead schedule, an overall schedule by stages, and a copy of the project plans. The 4-week look ahead schedule will be updated regularly.
This work is part of a $35 million transportation improvement project in Bedford and Billerica and is currently scheduled to be completed in 2023.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.