Beginning June 29, 2021, road work is starting in the Baldwin Rd area specifically on the following roads: Baldwin Rd (Margaret to Putney), Blossom Dr, Champa Rd, Courtland Ln, Ichabod Ln (Champa to Lois), Lois Ln, and Putney Circle.
- 7/29 excavating sidewalks and curbing on Blossom Dr. Will continue onto other roads.
- Upcoming: minor drainage structure installation on Baldwin Rd.
____________________
During the week of June 7, 2021:
- 6/7 Milling Schoolhouse Ln, concrete ramps on Fardon St and Glad Valley Dr.
- 6/8 Granite curb installation on Campbell Rd.
- 6/9 Granite curb installation on Marshall St.
- 6/10 Sidewalk forming & placement on Campbell Rd, Granite curb installation on Marshall St, Granite curb installation on Schoolhouse Ln, Sawcutting on Boston Rd from Alpine St to Forest Park Ave.
- 6/11 Leveling course paving on Schoolhouse Ln, Concrete ramps placement on Schoolhouse Ln and Marshall St.
- Next week Granite curb installation & concrete sidewalk on Boston Rd from Alpine St to Forest Park Ave.
____________________
During the week of June 1, 2021:
- 6/1 Top course paving on Fardon St.
- 6/2 Top course paving on Glad Valley Dr, driveway tie-ins on Fardon St, and granite curb installation on Marshall St.
- 6/3 Granite curb installation on Campbell Rd.
____________________
During the week of May 24, 2021:
- Reclaiming on Marshall Street and Elliot Street.
- Milling is scheduled May 26 on Schoolhouse Lane.
- RRFB flasher installations on Concord Rd and Faulkner St.
____________________
During the week of May 17, 2021, weather permitting:
- Loaming on edges of roadway on Glad Valley Drive.
- Grading for sidewalk on Glad Valley Drive.
- Drainage work on Elliot Street.
- Next week reclaiming on Marshall Street and Elliot Street.
____________________
During the week of May 3, 2021, weather permitting:
- Site work on Ed Hayes Way.
- Pavement leveling May 6 on Glad Valley Drive.
- Next week will be raising structures on Fardon Street and Glad Valley Drive.
____________________
During the week of April 26, 2021, weather permitting:
- The Contractor will be reclaiming and grading Fardon Street. We hope to have binder course pavement installed as soon as possible once grading is complete.
- Excavation of curbing and sidewalk on Glad Valley Drive.
- Pavement milling April 29 on Glad Valley Drive.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.