Beginning June 29, 2021, road work is starting in the Baldwin Rd area specifically on the following roads:  Baldwin Rd (Margaret to Putney), Blossom Dr, Champa Rd, Courtland Ln, Ichabod Ln (Champa to Lois), Lois Ln, and Putney Circle.  

  1. 7/29 excavating sidewalks and curbing on Blossom Dr.  Will continue onto other roads.
  2. Upcoming: minor drainage structure installation on Baldwin Rd.

____________________

During the week of June 7, 2021:  

  1. 6/7 Milling Schoolhouse Ln, concrete ramps on Fardon St and Glad Valley Dr.
  2. 6/8 Granite curb installation on Campbell Rd.
  3. 6/9 Granite curb installation on Marshall St.
  4. 6/10 Sidewalk forming & placement on Campbell Rd, Granite curb installation on Marshall St, Granite curb installation on Schoolhouse Ln, Sawcutting on Boston Rd from Alpine St to Forest Park Ave.
  5. 6/11 Leveling course paving on Schoolhouse Ln, Concrete ramps placement on Schoolhouse Ln and Marshall St.
  6. Next week Granite curb installation & concrete sidewalk on Boston Rd from Alpine St to Forest Park Ave.

____________________

During the week of June 1, 2021:  

  1. 6/1 Top course paving on Fardon St.
  2. 6/2 Top course paving on Glad Valley Dr, driveway tie-ins on Fardon St, and granite curb installation on Marshall St.
  3. 6/3 Granite curb installation on Campbell Rd.

____________________

During the week of May 24, 2021:  

  1. Reclaiming on Marshall Street and Elliot Street.
  2. Milling is scheduled May 26 on Schoolhouse Lane.
  3. RRFB flasher installations on Concord Rd and Faulkner St.

____________________

During the week of May 17, 2021, weather permitting:  

  1. Loaming on edges of roadway on Glad Valley Drive.
  2. Grading for sidewalk on Glad Valley Drive.
  3. Drainage work on Elliot Street.
  4. Next week reclaiming on Marshall Street and Elliot Street.

____________________

During the week of May 3, 2021, weather permitting:  

  1. Site work on Ed Hayes Way.
  2. Pavement leveling May 6 on Glad Valley Drive.
  3. Next week will be raising structures on Fardon Street and Glad Valley Drive.

____________________

During the week of April 26, 2021, weather permitting:  

  1. The Contractor will be reclaiming and grading Fardon Street.  We hope to have binder course pavement installed as soon as possible once grading is complete.
  2. Excavation of curbing and sidewalk on Glad Valley Drive.
  3. Pavement milling April 29 on Glad Valley Drive.