On Monday, June 15, 2020, weather permitting, the Contractor will be paving Tercentennial Drive and Russet Road.
-------------------
On Tuesday, June 9, 2020 and Wednesday, June 10, 2020, weather permitting, the Contractor will be paving Baldwin Road (from Kimbrough Road to Margaret Lane).
-------------------
On Monday, June 8, 2020, weather permitting, the Contractor will be paving Nashua Road (from Treble Cove Road to Stag Drive).
-------------------
On Tuesday June 2, 2020, weather permitting, the Contractor will be paving Brandon Street (dead end to Liberty Dr), Walton Street (Juniper St to Nashua Rd), and Kenwood Street (Juniper St to Nashua Rd).
-------------------
Ongoing work the Week of May 4, 2020, weather permitting:
- Reclamation and grading on Brandon Street followed by binder course paving.
- Leveling course paving on Nashua Road starts on Tuesday.
-------------------
Starting Monday, April 27, 2020, the Contractor plans to begin work on Nashua Road between Hawks Ridge Road and the Concord River Bridge. Work will occur between 7:30AM and 4:00PM daily. A detour will be in place to guide traffic around the work area.
The approximate schedule is as follows:
Week of April 27 - pavement milling
Week of May 4 - paving leveling course
May 11-May 29 - granite curb installation
Nashua Rd Area Map Existing sidewalk will be replaced. No new sidewalk will be built on Nashua Rd at this time - this is currently being designed and permitted.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.