Posted on: April 24, 2020

[ARCHIVED] Roadway Management (Updated 5/4/20)

Ongoing work the Week of May 4, 2020, weather permitting:  

  1. Reclamation and grading on Brandon Street followed by binder course paving.
  2. Leveling course paving on Nashua Road starts on Tuesday.

-------------------

Starting Monday, April 27, 2020, the Contractor plans to begin work on Nashua Road between Hawks Ridge Road and the Concord River Bridge.  Work will occur between 7:30AM and 4:00PM daily.  A detour will be in place to guide traffic around the work area.

The approximate schedule is as follows:

Week of April 27 - pavement milling

Week of May 4 - paving leveling course

May 11-May 29 - granite curb installation

Nashua Rd Area Map  Existing sidewalk will be replaced. No new sidewalk will be built on Nashua Rd at this time - this is currently being designed and permitted.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.