Starting Monday, April 27, 2020, the Contractor plans to begin work on Nashua Road between Hawks Ridge Road and the Concord River Bridge.  Work will occur between 7:30AM and 4:00PM daily.  A detour will be in place to guide traffic around the work area.

The approximate schedule is as follows:

Week of April 27 - pavement milling

Week of May 4 - paving leveling course

May 11-May 29 - granite curb installation

Nashua Rd Area Map  Existing sidewalk will be replaced. No new sidewalk will be built on Nashua Rd at this time - this is currently being designed and permitted.