The work includes the replacement of approximately 2,200 feet of water main on Baldwin Road from Little John Drive to Biscayne Drive. The Contractor, R&D Site Development, plans to start work associated with the project on May 20. They anticipate approximately 6 weeks of time to perform the work associated with the project. The project's substantial completion date is June 30, 2019.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.