News Flash Home
The original item was published from 3/8/2019 10:31:30 AM to 3/21/2019 12:42:23 PM.

News Flash

Public Works

Posted on: January 1, 2019

[ARCHIVED] Middlesex Turnpike Phase 3

Work is planned to start up again on Monday, March 11.

Current activity in Billerica includes: (March 8 Update)

  1. Water hydrant relocations.

  2. Installation of Mechanically Stabilized Slope between Lexington Road and Manning Road.

  3. Excavate and grade Stormwater Basin K north of Manning Road.

  4. Installation of drainage north of Manning Road.

Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below.  We have included  a 3-week look ahead schedule, an overall schedule by stages,and a copy of the project plans.  The 3-week look ahead schedule will be updated regularly.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.


Project Page

Contact Us
Facebook Twitter Email

Other News in Public Works