News Flash Home
The original item was published from 5/20/2020 3:06:00 PM to 5/29/2020 2:15:21 PM.

News Flash

Public Works

Posted on: October 17, 2019

[ARCHIVED] Sewer Contract 36 (Needs Area 3) (Updated 5/4/20)

Ongoing work the Week of May 11, 2020, weather permitting:  

  1. Asphalt berm installation.

------------------

Ongoing work the Week of May 4, 2020, weather permitting:  

  1. Binder course paving on Moosewood, Broadleaf, Sequoia, Market, Gove, Gail Ann.  All binder course should be completed this week.
  2. Structure adjustments area wide.
  3. Granite curb installation on Pond Street should be complete by Thursday.
  4. Concrete sidewalk pouring on Pond Street begins on Friday starting at Salem Road.

------------------

April 27, 2020 binder course paving begins on Tomahawk Drive and the side streets off Tomahawk Drive.  Paving will occur daily, weather permitting, until all roads in the neighborhood have binder course.

------------------

April 21, 2020 granite curb installation begins on Pond Street.

------------------

April 16-17, 2020 grading on Sumac Street and Ironwood Street.  The week of April 21, reclaimer will be working on Moosewood Street, Richards Street, Sequoia Street and Gove Road.  Paving crew returns the week of April 27 to pave Tomahawk Drive and the side streets off Tomahawk Drive.

------------------

Thursday, April 9, 2020 binder course paving on Pond Street, Eveready Circle, Race Street, and Vine Street is canceled.  This work is rescheduled to Friday, April 10, 2020 and Saturday, April 11, 2020.  The reclaimer is moving to Tomahawk Drive Thursday, April 9 and Friday, April 10.  Also, Sumac Street will be reclaimed on Saturday, April 11, 2020.  Due to anticipated weather, work is canceled on Monday, April 13, 2020.

------------------

On Thursday, April 9, 2020, the Contractor plans to begin road work on Gail Ann Drive.  Work will occur between 7AM and 3PM daily.  The Contractor will try to minimize delays to you and maintain temporary access to your properties during the work.  Advanced notice will be given if vehicles need to be moved or parked elsewhere for a short duration.

------------------

On Thursday, April 9, 2020 and Friday, April 10, 2020 binder course paving is scheduled on Pond Street, Eveready Circle, Race Street, and Vine Street.  Work will occur between 7AM and 4PM.  The road will be closed to all through and local traffic.  Local traffic within the work limits should plan to move their vehicles prior to the start of work each day.  If inclement weather postpones paving work, work will be scheduled for the next suitable day.

------------------

Starting Monday, March 30, 2020, the Contractor plans to begin road work associated with the project.  Work will occur between 7AM and 3PM daily.  The work will be  broken into 3 phases as follows:

Phase 1:  Pond Street, Challenger, Tamarac

Phase 2: Tomahawk Drive and side streets, Sumac, Ironwood, Crestwood, and Gail Ann

Phase 3: Moosewood, Sequoia, Gove, Bayberry, Market, Broadleaf, Richards, Race, Vine, Eveready

Reclaiming will begin on Pond Street on Monday, March 30.  Pond Street will be closed and traffic detours will be in place for thru traffic.  The easement areas on Richards Street and Tomahawk Drive will be open for local traffic to access the neighborhood.

Stay up to date on the progress of the Sewer Contract 36 Project by checking out our project page link below.  We have included a 3-month schedule and a copy of the project plans.  The schedule will be updated regularly.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.

Detour Map

Project Page

Contact Us
Facebook Twitter Email

Other News in Public Works