Current activity in Billerica includes: (September 24 Update)
- Ongoing work installing the mechanically stabilized slope near the project limits north of Manning Road.
- The Contractor anticipates overnight work from 9pm Fri 10/12 to 5pm Sat 10/13 to install a 48" culvert across Lexington Road.
- Week of Oct 8, various drainage installation work is scheduled near 900 Middlesex Turnpike.
Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below. We have included a 3-week look ahead schedule, an overall schedule by stages,and a copy of the project plans. The 3-week look ahead schedule will be updated regularly.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.
Project Page