[ARCHIVED] Middlesex Turnpike Phase 3

September 7 Update:  Current activity includes removal of unsuitable soils and installing material for utility pole pads, new roadway edge, and drainage culverts. Wall 8 construction is ongoing near BVW 15.  Excavation work within the Town's Cabot site is in progress.

Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below.  We have included  a 3-week look ahead schedule, an overall schedule by stages,and a copy of the project plans.  The 3-week look ahead schedule will be updated regularly.


If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.