July 23 Update: Grubbing along the ROW has primarily been completed. The Contractor has completed paving operations for a temporary pavement wedge to shift the roadway crown. Blasting, geotechnical borings, and preparation for utility pads is ongoing. The Contractor has installed the sheeting at BVW 15 and dewatering is ongoing during Wall 8 construction.
Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below. We have included a 3-week look ahead schedule, an overall schedule by stages,and a copy of the project plans. The 3-week look ahead schedule updates will be ongoing.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.