News Flash Home
The original item was published from 5/13/2016 9:57:00 AM to 5/26/2016 5:56:35 PM.

News Flash

Public Works

Posted on: May 13, 2016

[ARCHIVED] Boston Rd. Improvements - Week of May 16

For the week of May 16, the Contractor will be continuing with utility conduit and drainage installation.

Conduit installation will run from the electric manhole at 409 Boston Road to the electric manhole at the intersection with Boston Road/Cummings Street. We anticipate crossing the Cummings Street/O'Connors intersection on Wednesday/Thursday. You should plan additional time for delays, and some traffic will need to be detoured.

A second crew will be continuing with drainage installation on the west side of Boston Road.

On-roadway work will run daily between 7:00am to 3:00pm Monday through Friday.

You can find an overview of the project on the project page.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.

Contact Us
Facebook Twitter Email

Other News in Public Works