Posted on: April 29, 2016

[ARCHIVED] Boston Road Improvements

For the week of May 2, the Contractor will be performing drainage and utility conduit installation.

One lane of traffic will be maintained in each direction through the duration of construction. On-roadway work will run daily between 8:00am to 3:00pm Monday through Friday.

The completion date for the project is September 8, 2017. We are planning for the various utilities to begin individual work associated with the undergrounding of overhead wires sometime in the Spring of 2017.

You can find an overview of the project on the project page.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.