For the week of April 25, expect to see mobilization of equipment and delivery of materials. Tree cutting will be performed, and various preparatory work. On-road work is expected to begin next week, starting with drainage and conduit installation.
One lane of traffic will be maintained in each direction through the duration of construction. On-roadway work will run daily between 8:00am to 3:00pm Monday through Friday.
The completion date for the project is September 8, 2017. We are planning for the various utilities to begin individual work associated with the undergrounding of overhead wires sometime in the Spring of 2017.
You can find an overview of the project on the project page.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.