Paving base course is scheduled for July 6 and 7 on the section of Allen Road between Riverdale Road and Boston Road. On July 10, curb installation begins in this section. Paving binder course will follow tentatively the week of July 17.
You can find an overview of the project on the project page. If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.