During the week of November 7, the Contractor is working on graveling the roadway between Webb Brook Road and Ravine Road in preparation for paving. Paving is tentatively scheduled for the end of the week of November 14 or early the week of November 21.
We anticipate that there may be minor on road work during the winter as weather permits.
You can find an overview of the project on the project page.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.