News Flash Home
The original item was published from 4/29/2016 12:34:00 PM to 4/29/2016 1:13:04 PM.

News Flash

Public Works

Posted on: April 8, 2016

[ARCHIVED] Allen Road Reconstruction Project Info

J. Tropeano, Inc. has been given a Notice to Proceed.

Work will start with survey stakeout of the construction baseline, proposed edge of roadway, and proposed back of sidewalk. Early work will include installation of erosion controls, safety signage, and layout of the new utility pole locations. 56 utility poles will be moved as part of the project. The contract time is 730 calendar days from Notice to Proceed, with a completion date of October 18, 2018.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.

Contact Us
Facebook Twitter Email

Other News in Public Works