J. Tropeano, Inc. has been given a Notice to Proceed.
Work will start with survey stakeout of the construction baseline. Early work will include layout of the new utility pole locations, 56 utility poles will be moved as part of the project. The contract time is 730 calendar days from Notice to Proceed, with a completion date of October 18, 2018.