[ARCHIVED] Allen Road Phase 1 and 2 (Updated 5/9)

Contractor is in progress of addressing the lawns on Allen Rd Phase 1.  According to the Contractor, everything else on the punch list is complete.

On Allen Rd Phase 2 (Boston Rd work), the Contractor won't startup work again until Mid to late June.  The traffic signal won't be activated until late summer at the earliest.  They plan to complete all work this season.  

You can find an overview of the project, including the contract plans on the project page. If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.