The week of July 25, the Contractor will be installing water services on Rangeway Road between Boston Road and Chelmsford Road (Route 129). Once complete, the temporary bypass water main will be removed.
The Contractor is also working on Rangeway Road installing sewer from Chelmsford Road headed toward the Bridge. This section will be closed daily as necessary, and the detour will be in place.
Various work in other areas may also occur at the same time, and is subject to change. Stay posted here. Work will be ongoing through this construction season, ending in November.
You can find an overview of the project on the project page.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.