News Flash Home
The original item was published from 9/15/2015 9:53:00 AM to 9/23/2015 6:25:01 PM.

News Flash

Public Works

Posted on: September 15, 2015

[ARCHIVED] 2015 Water Main Improvements

As part of our water main improvements program, in 2015 we plan on replacing the water mains on the following roadways:

Christina Avenue from Cook Street to Pinehurst Avenue

Dee Dee Circle from Christina Avenue to the cul-de-sac

Lupine Lane from Edgar Road to Ossamequin Road

Water main work on Lupine Lane is completed. Binder course paving is complete. Remainin work includes driveway tie-ins, structure adjustments, and loam & seeding. Work on Christina Avenue and Dee Dee Circle is ongoing.

Per contract, the completion date for water main installation is October 1, 2015. Top coat paving on Lupine Lane will be completed by June 1, 2016. Paving on Christina Avenue is currently not in the contract.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us.

Facebook Twitter Email

Other News in Public Works