News Flash Home
The original item was published from 8/21/2015 3:02:00 PM to 9/15/2015 9:53:58 AM.

News Flash

Public Works

Posted on: August 21, 2015

[ARCHIVED] 2015 Water Main Improvements

As part of our water main improvements program, in 2015 we plan on replacing the water mains on the following roadways:

Christina Avenue from Cook Street to Pinehurst Avenue

Dee Dee Circle from Christina Avenue to the cul-de-sac

Lupine Lane from Edgar Road to Ossamequin Road

Work on Lupine Lane is ongoing, we anticipate the main installation will be completed during the week of August 24. Water service connections to the new main will follow. Work on Christina Avenue and Dee Dee Circle is tentatively scheduled to begin the week of August 24, with the installation of the temporary water bypass.

Per contract, the completion date for water main installation is October 1, 2015. Paving binder course on Lupine Lane only will be done by October 15, 2015, with top coat paving completed by June 1, 2016. Paving on Christina Avenue is currently not in the contract.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us.

Facebook Twitter Email

Other News in Public Works