As part of our water main improvements program, in 2015 we plan on replacing the water mains on the following roadways:
Christina Avenue from Cook Street to Pinehurst Avenue
Dee Dee Circle from Christina Avenue to the cul-de-sac
Lupine Lane from Edgar Road to Ossamequin Road
R&D Site Development has been awarded the contract. We anticipate that construction will begin on Lupine Lane. Work will begin the week of August 10 with the installation of the temporary water bypass. Work on Christina Avenue and Dee Dee Circle is tentatively scheduled to begin the second week in September. Per contract, the completion date for water main installation is October 1, 2015. Paving binder course on Lupine Lane only will be done by October 15, 2015, with top coat paving completed by June 1, 2016. Paving on Christina Avenue is currently not in the contract.
If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us.