In July 2016, the Town submitted the 25% Design Plans and 25% Right of Way Plans to MassDOT.
The path cross section will consist of a 10-foot wide asphalt shared use path (SUP) with two foot shoulders, for a total width of 14 feet. Included in the project is the construction of a 950-foot long boardwalk; a 30-foot high pedestrian ramp structure; drainage crossings; four roadway crossings with RRFB's; advance roadway signage and pavement markings; and a four car parking lot and trailhead at Middlesex Turnpike.
The conceptual cost estimate is approximately $8,270,000.00.
Additional information on the project including the 25% Design Plans can be viewed on the project page.