Posted on: November 1, 2016

[ARCHIVED] Yankee Doodle Bike Path - Updated Nov 1

In July 2016, the Town submitted the 25% Design Plans and 25% Right of Way Plans to MassDOT.

The path cross section will consist of a 10-foot wide asphalt shared use path (SUP) with two foot shoulders, for a total width of 14 feet. Included in the project is the construction of a 950-foot long boardwalk; a 30-foot high pedestrian ramp structure; drainage crossings; four roadway crossings with RRFB's; advance roadway signage and pavement markings; and a four car parking lot and trailhead at Middlesex Turnpike.

The conceptual cost estimate is approximately $8,270,000.00.

Additional information on the project including the 25% Design Plans can be viewed on the project page.

If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.