Sewer Contract 36 (Needs Area 3)

The East Billerica Sewer Extension – Contract 36 Project includes the installation of approximately 22,000 linear feet of gravity sewer main, the installation of a sewer pumping station, approximately 5,500 linear feet of sewer force main, 13,000 linear feet of water main replacement, 5,900 linear feet of sidewalk construction, associated paving and all
materials and equipment, services and construction inherent to the Work.  

This project will service approximately 262 properties in the lower Pond Street area, Needs Area 3.  Baltazar Contractors, Inc. was awarded the construction contract with a start date of July 30, 2018.  Substantial Completion is scheduled for February 15, 2020 with a Final Completion date of July 24, 2020.  The construction cost $11,611,448.70 (base +all alts).

Contractor's Schedule (3 Months)

C36_Final_Plans