Middlesex Turnpike Phase 3

August 9 Update:  Current activity includes blasting, geotechnical borings, and preparation for utility poles installation. Wall 8 construction is ongoing near BVW 15.


Stay up to date on the progress of the Middlesex Turnpike Project by checking out our project page link below.  We have included  a 3-week look ahead schedule, an overall schedule by stages,and a copy of the project plans.  The 3-week look ahead schedule updates will be ongoing.


If you have any questions, telephone the Engineering Division at 978-671-1300 or contact us below.